The New Homes Program title verification (M3) Milestone was created in the spirit of flexibility, as a homeowner appearing on title for a new build can be a delayed process.

When does title need to be run?

Title can be run at anytime during the Milestone process (M0, M1, M2, M3).

A rejection for title prior to the M3 Milestone will not halt or prevent the project from moving forward to the next milestone

Title must be run by M3 to complete and close out the Milestone Requirements Process for the LightReach New Homes Program.

What type of documentation is accepted for New Homes title?

All homeowners must complete title verification. A homeowner may be prompted to upload title verification documents through their web portal

Acceptable documents:

  • Closing Documents on the home

  • Original deed or deed of trust

  • Most recent tax property bill

  • Mortgage statement less than 60 days old

Where can I complete Title verification?

Homeowner can upload title verification documents through their web portal